O&G Industries – Beacon Falls
O&G Industries · Under construction · Near Gruber Road & Railroad Avenue
Two-story, 294,164 sq ft facility on 47 acres of a former sand mine, approved unanimously by Beacon Falls residents in 2022. Under construction as of 2026. Includes an on-site fuel cell for power.
Lifecycle timeline
ObservedConfirmed events only, with sources. Timing and observation, not cause and effect.
~January 2022
Beacon Falls approves 32 MW data center
Construction firm gains approval for a 32 MW, 294,164 sq ft data center in Beacon Falls, CT.
Source
Estimated water use
EstimateNo published cooling system type is available yet, so no estimate can be produced. This is intentional — the estimate is only shown when it can be backed by a published figure.
Observed hydrologic data
ObservedFrom nearby USGS and NOAA monitoring stations, refreshed monthly. Dashed lines mark lifecycle milestones — timing only, not causation.
Groundwater level (ft below surface)
USGS CT-WB 93 (413134073021701)
Groundwater level (ft below surface)
USGS CT-HM 448 (412541072542001)
Groundwater level (ft below surface)
USGS CT-HM 445 (412423072542801)
Groundwater level (ft below surface)
USGS CT-SB 42 (412916073121701)
Groundwater level (ft below surface)
USGS CT-SB 39 (413002073131001)